Turbidity Scheme

Contract Title:
Raw / Final Turbidity Scheme - Across 53 Sites
Client:
Morrison Utility Services / Southern Water
Value:
£218,870
Type of Work:
Design, Supply, Installation, Commissioning and Training
Description

Prior to work, a feasibility study was to be carried out.

Once complete, the works included:

  • The design, supply and installation of PLC controlled raw turbidity panels to monitor the turbidity in the water
  • Design and installation of all mechanical pipework and electrical installation of turbidity monitoring systems
  • The supply and installation of all associated mechanical pipework and electrical field cabling
  • Final Testing, training and commissioning was then carried out