Hurdcott
Contract Title:
Hurdcott Sewage Treatment Works
Client:
Wessex Water
Value:
£140,858
Type of Work:
Design, Supply, Installation and Commissioning
Description
As part of the National Environmental programme for AMP 4, Phosphorous removal is required to meet an annual mean of
1mg/1.
Existing sewage works are also exceeding its consented DWF. As part of our contract Marray’s supplied the MCC, Ferric
Dosing Panel.
The scope of works was for the Design, Management, Cable containment, Installation, testing and commissioning.
1mg/1.
Existing sewage works are also exceeding its consented DWF. As part of our contract Marray’s supplied the MCC, Ferric
Dosing Panel.
The scope of works was for the Design, Management, Cable containment, Installation, testing and commissioning.
Murray Control Systems Limited
Unit 8a & 8b
Tower Industrial Estate
Tower Lane, Eastleigh
Hampshire
SO50 6NZ
Email : info@murraycontrolsystems.co.uk
Tel: 023 8065 0377
Fax: 023 8061 0558

023 8065 0377